Team:DTU-Denmark/Timeline
From 2013.igem.org
(Difference between revisions)
(→August) |
(→August) |
||
Line 67: | Line 67: | ||
* Transformed arabinose inducible promoter for use with [[Team:DTU-Denmark/pBAD_SPL|pBAD synthetic promoter library]] | * Transformed arabinose inducible promoter for use with [[Team:DTU-Denmark/pBAD_SPL|pBAD synthetic promoter library]] | ||
* One Nir fragment has been amplified with USER primers (changed DMSO, Mg, temperature, etc), one to go | * One Nir fragment has been amplified with USER primers (changed DMSO, Mg, temperature, etc), one to go | ||
- | * [[Team:DTU-Denmark/Experiment2| | + | * Repeated the [[Team:DTU-Denmark/Experiment2|experiment to characterize anaerobic production of N<sub>2</sub>O]] to try to reproduce results |
'''Week 34''' | '''Week 34''' | ||
- | |||
* Ran first biolector experiment to characterize [[Team:DTU-Denmark/pBAD_SPL|pBAD synthetic promoter library]] | * Ran first biolector experiment to characterize [[Team:DTU-Denmark/pBAD_SPL|pBAD synthetic promoter library]] | ||
+ | * Completed first draft of presentation | ||
+ | * Completed first draft of poster | ||
'''Week 35''' | '''Week 35''' | ||
- | * Attended Scandinavian meetup in Odense hosted by SDU team | + | * Attended Scandinavian meetup in Odense hosted by SDU team. Thank you SDU for a great weekend! |
- | * | + | * Conducted another set of biolector experiments to characterize more colonies from the [[Team:DTU-Denmark/pBAD_SPL|pBAD synthetic promoter library]] |
- | * | + | * Sent [[Team:DTU-Denmark/pBAD_SPL|pBAD SPL]] samples for sequencing |
- | + | * Conducted [[Team:DTU-Denmark/Experiment4 | experiment to characterize AMO and HAO transformants]] | |
- | * | + | * Decided on project title: Reqiuem for a Stream |
- | + | * Wrote the project [[Team:DTU-Denmark/Project|abstract]] | |
- | + | ||
- | * | + | |
- | * | + | |
* Reviewed presentation with Julie, who gave us very good advice on pitching our project | * Reviewed presentation with Julie, who gave us very good advice on pitching our project | ||
- | |||
===September=== | ===September=== |
Revision as of 10:47, 29 September 2013
Timeline
Contents |
Project Timeline
January
- 2013-01-15 Budget completed
- 2013-01-29 Human Practices: Workshop for highschool students
February
- 2013-02-25 Project selected: Conversion of ammonia to nitrous oxide in E. coli
March
- 2013-03-11 Biobrick workshop hosted for KU and SDU
- 2013-03-13 Project kickoff meeting with supervisors
April
- 2013-04-15 Team contract written and signed
- 2013-04-28 Human Practices: Held second workshop for highschool students
May
- 2013-05-29 Hello World pilot project kicked off
June
- 2013-06-04 Team competency mapping
- 2013-06-09 Work on wiki started
- 2013-06-29 Team BBQ
July
Week 27
- Hello World project complete and successful. From a cytoplasmic extraction, we have observed GFP in the periplasm and RFP in the cytoplasm.
- Conducted the toxicity experiment and completed data analysis: average ammonia concentrations in wastewater are not toxic to E. coli.
Week 28
- Designed, ordered and received primers to extract genes from Nitrosomonas and Pseudomonas
- Began work on cloning genes out of Nitrosomonas europaea and Pseudomonas aeruginosa. All isolations successful so far except for Nir.
Week 29
Week 30
- Ordered new primers to extract Nir gene in two pieces.
- Despite successful PCR and transformation of AMO, HAO and cytochromes, we only have viable colonies for the cytochromes. Expect that this is due to the fact that we are expressing periplasmic and membrane proteins, which is causing excessive stress on the cells.
- Began work on pBAD synthetic promoter library so that we will be able to induce a low level of expression of our periplasmic genes.
Week 31
- Saturday BBQ with KU
August
Week 32
- The week no PCR worked -- ran 96 PCRs with varying conditions to debug what is not working
- Conducted the experiment to characterize anaerobic production of N2O in native E. coli
- Began work on kinetic models of the aerobic and anaerobic pathways
- Began putting together our presentation
Week 33
- Began having daily meetings
- Transformed arabinose inducible promoter for use with pBAD synthetic promoter library
- One Nir fragment has been amplified with USER primers (changed DMSO, Mg, temperature, etc), one to go
- Repeated the experiment to characterize anaerobic production of N2O to try to reproduce results
Week 34
- Ran first biolector experiment to characterize pBAD synthetic promoter library
- Completed first draft of presentation
- Completed first draft of poster
Week 35
- Attended Scandinavian meetup in Odense hosted by SDU team. Thank you SDU for a great weekend!
- Conducted another set of biolector experiments to characterize more colonies from the pBAD synthetic promoter library
- Sent pBAD SPL samples for sequencing
- Conducted experiment to characterize AMO and HAO transformants
- Decided on project title: Reqiuem for a Stream
- Wrote the project abstract
- Reviewed presentation with Julie, who gave us very good advice on pitching our project
September
Week 36
- Have biobricks for AMO and cytochromes (are going to sequence these), the others are coming.
- Running last biolector experiment today
- sequencing for SPL is in progress
- Kristian is working on a page in the parts registry for the parts registry
- first draft of presentation completed
- first draft of poster complete
- modelling of kinetics and design of a reactor: using Continuous Stirred Tank Reactor
- Began reactor design -- ask Mikael Rordham in 223 for 2 1L chemostats
Week 37
- biobricks -- have 2 that are fine: AMO and cytochromes
- redo colony pcr with sequencing primers to verify
- Nir experiment on friday
- Planning for bioreactor experiment
- Human Practices: Attended BioPeople event "The Basics and the Best" on IP and patent law
Week 38
- Filmed "Bricks of Knowledge" video on USER cloning for KU team
- Biobricks mailed
- tat signal peptide
- amo
- cytochromes
- arabinose promoter biobrick not made -- Kristian and Henrike will make this in the next few days
- Bioreactor experiment started this morning, will finish at 10pm tonight.
Week 39
- Hackathon intensive to complete wiki 28th of Sept
- Nir experiment -- Kasia and Ariadne will do this on Thursday
- Video in progress
- Reviewed poster v2
October
Week 40
- Wiki complete!