Team:Poznan-BioInf/Book
From 2013.igem.org
(prolog update) |
(june update) |
||
Line 53: | Line 53: | ||
and at the end of April 2013 we've received decision that we are granted 200 000 zlotys. | and at the end of April 2013 we've received decision that we are granted 200 000 zlotys. | ||
</p><p> | </p><p> | ||
- | May. We've officially signed the funding agreement and we're waiting for approval. Unfortunately, two thirds of | + | May. We've officially signed the funding agreement and we're waiting for approval. Unfortunately, two thirds of our team are working on end-of-term exams |
and Bachelor's theses so... we received BioBricks and we're waiting for decision that we can administer our funds. | and Bachelor's theses so... we received BioBricks and we're waiting for decision that we can administer our funds. | ||
That month We are looking for wet lab instructor and place, where we could spend summer. We are going to have a meeting with one of our professor, who we are going | That month We are looking for wet lab instructor and place, where we could spend summer. We are going to have a meeting with one of our professor, who we are going | ||
Line 67: | Line 67: | ||
<p> | <p> | ||
- | We've started to trying to equip our lab. Because we | + | We've started to trying to equip our lab. Because we study on two universities: Poznan University of Technology (where we officially belong) |
and Adam Mickiewicz University, we had some problems with the administration. On Poznan University of Technology there is no wet laboratory specialized | and Adam Mickiewicz University, we had some problems with the administration. On Poznan University of Technology there is no wet laboratory specialized | ||
- | at microbiological research. That's why we are | + | at microbiological research. That's why we are forced to work on Adam Mickiewicz University. |
</p><p> | </p><p> | ||
- | Problems have started to rise. Due to Polish law we can't make order as fast as we think and as we would like to. | + | Problems have started to rise. Due to Polish law we can't make any order as fast as we think and as we would like to. |
- | + | Every single one of our orders needs to be signed by four various officials. What is more, we are obliged to contact three various manufacturers or | |
- | + | distributors of every product/service to get pricings of their products. Unfortunately to us, the holidays begin so we're going to encounter some serious trouble with making appointments. | |
</p> | </p> | ||
<h4>July.</h4> | <h4>July.</h4> |