Line 33: | Line 33: | ||
* 2013-07-06 "Hello World" pilot project complete | * 2013-07-06 "Hello World" pilot project complete | ||
+ | |||
+ | * Week 27 | ||
+ | **Hello World project is successful. From a cytoplasmic extraction, we have observed GFP in the periplasm and RFP in the cytoplasm. See a nice picture here: https://2013.igem.org/Team:DTU-Denmark/Notebook/6_July_2013 | ||
+ | ** Biolector experiment complete, initial data analysis complete. See some graphs here: https://2013.igem.org/Team:DTU-Denmark/ToxicityExperiment | ||
+ | ** Made media and began growing Nitrosomonas culture | ||
+ | ** Designed, ordered and received primers to extract genes from Nitrosomonas and Pseudomonas | ||
===August=== | ===August=== | ||
===September=== | ===September=== |
Revision as of 21:56, 9 July 2013
Contents |
Timeline
January
- 2013-01-15 Budget completed
- 2013-01-29 Human Practices: Workshop for highschool students
February
- 2013-02-25 Project selected: Conversion of ammonia to nitrous oxide in E. coli
March
- 2013-03-11 Biobrick workshop hosted for KU and SDU
- 2013_03_13 Project kickoff meeting
April
- 2013-04-15 Team contract signed
- 2013-04-28 Human Practices: Outreach for highschool students
May
- 2013-05-29 "Hello World" pilot project kicked off
June
- 2013-06-04 Team competency mapping
- 2013-06-09 Work on wiki started
- 2013-06-29 Team BBQ
July
- 2013-07-06 "Hello World" pilot project complete
- Week 27
- Hello World project is successful. From a cytoplasmic extraction, we have observed GFP in the periplasm and RFP in the cytoplasm. See a nice picture here: https://2013.igem.org/Team:DTU-Denmark/Notebook/6_July_2013
- Biolector experiment complete, initial data analysis complete. See some graphs here: https://2013.igem.org/Team:DTU-Denmark/ToxicityExperiment
- Made media and began growing Nitrosomonas culture
- Designed, ordered and received primers to extract genes from Nitrosomonas and Pseudomonas